Sunday, August 26, 2012

Week 10

Week 10: August 13-16
 
Tuesday, Aug 14th the crane came and they put up the trusses.



That week they also put up most of the plywood on the roof.

They framed the walls that the plumber would need framed. The plumber was scheduled to be here the following Monday (Aug 20th).
 
This picture is taken from the living/family room. The back corner is Celeste's room and then the bathroom is the framed room there.

The master bathroom. HUGE!

Laundry room (next to the master bath)

The family room

It's starting to look like a house! Yipee!


2 comments:

Harrison's said...

Yay! It looks awesome! So fun to see so much progress.

emily said...

That looks great. I hope we catch up to you soon. I'm ready to have a place to live. When is it scheduled to be done?