July 18th: The lumber truck delivered all our wood for framing. Our contractor hooked up an outlet from our electricity so they could start laying the floor.
July 19-20: They laid our floor. Can I tell you how great it is to see progress?!
This is the basement. It will be an unfinished basement for now. I believe the only thing they will be framing is the bearing wall you see here.
Our trusses are scheduled to be made August 4th. We're hoping and praying a time slot comes available earlier so we can get them sooner. I'm ready for some walls and for it to look like a house!