Tuesday, July 3, 2012

Weeks 3 and 4

Week 3: June 25-29
John made the french drain and spread gravel all over the basement floor in preparation to pour the cement floor

June 29th the plumber came and did the first of the plumbing work.


Week 4: June 2nd
The cement floor was poured

Next step is framing! However, they have to wait until we have electricity before they can start that. We had a hold up with the electricity. There was a miscommunication as we thought we had electric to our lot. The truth is they put in the "backbone" but there is no electricity. We got to purchase a transformer and get electricity to not only our lot but the lot next to us. Wonderful surprise to us!

No comments: